Shapez 2 – 12 Lane MAM + 12 Lane CMAM Blueprint

12 Lane MAM + 12 Lane CMAM

By MathAndCarnage.

Here’s Blueprints for my MAM and CMAM. This uses the new Fluid gates to reduce painting/crystalizing to a single platform per layer.

Some Timings:

MAM

  • First Item in Vortex = 3:50
  • All Lanes in Vortex = 4:37
  • One full Trainload produced (3240 items) = 5:57

CMAM

  • First Item in Vortex = 8:52
  • All Lanes in Vortex = 9:58
  • One full Trainload produced (3240 items) = 11:23

How does this compare to the current MAM state of the art? Seems pretty small for a 12 Lane system to me.

Click to enlarge…

I hope the above information was helpful.

Be the first to comment

Leave a Reply

Your email address will not be published.


*